DGFT➤Foreign Trade Policy 2023 in effect: claim the export incentive schemes you are eligible for with RASPCUSTOMS➤CBIC Customs Circulars updated: Expert advisory on classification & duty drawbackRoDTEP➤RoDTEP & RoSCTL Rates Revised: Calculate your refund & rebate eligibilityTRADE ALERT➤India-UK & UAE FTAs: Zero-duty tariff access for 97% of goods. Exporting abroad?DGFT NOTICE➤Advance Authorisation & EPCG Scheme compliance review open for Indian exportersADVISORY➤Book your free 30-minute EXIM & DGFT compliance consultation with RASP experts → DGFT➤Foreign Trade Policy 2023 in effect: claim the export incentive schemes you are eligible for with RASPCUSTOMS➤CBIC Customs Circulars updated: Expert advisory on classification & duty drawbackRoDTEP➤RoDTEP & RoSCTL Rates Revised: Calculate your refund & rebate eligibilityTRADE ALERT➤India-UK & UAE FTAs: Zero-duty tariff access for 97% of goods. Exporting abroad?DGFT NOTICE➤Advance Authorisation & EPCG Scheme compliance review open for Indian exportersADVISORY➤Book your free 30-minute EXIM & DGFT compliance consultation with RASP experts → DGFT➤Foreign Trade Policy 2023 in effect: claim the export incentive schemes you are eligible for with RASPCUSTOMS➤CBIC Customs Circulars updated: Expert advisory on classification & duty drawbackRoDTEP➤RoDTEP & RoSCTL Rates Revised: Calculate your refund & rebate eligibilityTRADE ALERT➤India-UK & UAE FTAs: Zero-duty tariff access for 97% of goods. Exporting abroad?DGFT NOTICE➤Advance Authorisation & EPCG Scheme compliance review open for Indian exportersADVISORY➤Book your free 30-minute EXIM & DGFT compliance consultation with RASP experts →

Book Your Free Export Consultation Now →

Book a call
Rasp International | Project Cargo

Project Cargo Handling in India: ODC Permits, Heavy Haulage and Breakbulk Shipping

How to move oversized or overweight machinery legally on Indian highways and onto a ship: the MoRTH online ODC permit, hydraulic trailer classes, route surveys, lashing and the vessel choice. Rasp International coordinates project moves through vetted heavy haulage, forwarding and customs broker partners across India.

Project cargo is equipment too large, too heavy or too valuable for standard containers: transformers, turbines, boilers, presses and plant modules.

Each move needs a permit, a trailer matched to the load, a surveyed route and a ship that can lift and secure it. Miss one and the cargo waits at the roadside or the quay while penalties run.

18 t
Maximum load per axle row on modular hydraulic trailers, MoRTH ODC circular of 27 October 2025
7 Days
Maximum route review time for HT-4 to HT-13 applications, same circular
4.75 m
Height above which an ODC route must avoid overhead structures, same circular
20+ Years
In international trade, with a family legacy that began in 2005

Verified as on 24 September 2026 against the MoRTH circular RW/NH-35072/01/2010-S&R(B)PT-2 dated 27 October 2025, GSR 414(E) dated 26 June 2020 and the Project Imports Regulations 1986.

The Short Answer on Project Cargo

An over dimensional consignment (ODC) is a single indivisible load that exceeds the road dimension limits in Rule 93 of the Central Motor Vehicles Rules 1989. An overweight consignment (OWC) exceeds the permitted weight. Moving either on a National Highway on a modular hydraulic trailer needs online permission from the Ministry of Road Transport and Highways (MoRTH) through its ODC portal.

The rule that decides everything: the permit covers one declared load, one trailer class and one route. Change any of the three and the move is no longer covered.

ItemKey facts
Road permissionOnline on the MoRTH ODC portal (morth-owc.nic.in) for single indivisible ODC and OWC loads on National Highways
Governing circularMoRTH circular dated 27 October 2025, which replaced the circulars of 17 January 2024 and 12 June 2024
Trailer classesModular hydraulic trailer combinations HT-1 to HT-13, with no more than 18 tonnes per axle row
Road dimension ruleCMVR Rule 93, amended by GSR 414(E) dated 26 June 2020
Lashing standard at seaIMO Code of Safe Practice for Cargo Stowage and Securing (CSS Code), resolution A.714(17) of 1991
Import sideProject Imports Regulations 1986 and heading 98.01 of the Customs Tariff

Why Project Cargo Punishes Small Errors

Under the 27 October 2025 circular, a trailer found with more than 18 tonnes on an axle row, or with dimensions much larger than declared, is held for 7 days. The applicant pays a fine of twenty times the permit fee and the transporter is barred from the portal for at least a year.

Rasp International does not own trailers or cranes. We brief the heavy haulage and forwarding partners in our network, check the declared dimensions against the drawings and track the permit, route and vessel booking together.

What Makes Cargo Over Dimensional

A load becomes ODC when the loaded vehicle would exceed the Rule 93 limits. GSR 414(E) dated 26 June 2020 set the current figures, as summarised by PIB on 1 July 2020.

DimensionNormal limit under Rule 93What it means for project cargo
Width2.6 mIndivisible loads may project 200 mm on each side, with conditions. Beyond that the load is ODC
Height, goods vehicle4.0 mMeasure the loaded trailer, not the machine alone
Height, indivisible loadUp to 4.75 mAbove 4.75 m the route must avoid overhead structures, road over bridges and underpasses
Height, container semi-trailer4.52 mOut of gauge cargo on a flat rack can cross it
Trailer length18.75 mPneumatic trailers can extend up to 50 m for long items such as wind turbine blades

Who Needs Project Cargo Planning and Who Does Not

  • Machinery exporters shipping presses, boilers, gensets or fabricated structures wider than 2.6 m.
  • EPC contractors and plant builders sending modules for overseas projects on a fixed delivery date.
  • Importers of capital goods bringing in plant under the project imports scheme or EPCG.
  • Anyone moving a single unit that cannot be dismantled, which is the only kind of load the ODC permit covers.

Who Does Not Need It

Machinery that fits a standard box or an open top within road limits moves as normal container cargo. Loads that can be split into road-legal pieces do not qualify, since the permit covers single indivisible units only.

Project Cargo Services Through Our Partner Network

Specialist partners do the lifting and hauling. Our team keeps permit, route, customs and vessel in step.

Containers

Flat Rack and Open Top

Out of gauge cargo that still ships as a container.

See container moves
Freight

Breakbulk and RoRo Booking

Vessel choice, Incoterms and bills of lading.

Read freight advisory
Clearance

Customs for Heavy Units

Shipping bills and examination for non-containerised cargo.

Read the clearance guide
Supply Chain

Packing and Insurance

Crating, preservation and marine cover.

Plan the full chain
Capital Goods

EPCG for Imported Machinery

Zero duty import of capital goods against export obligation.

Check EPCG
Inputs

Advance Authorisation

Duty free inputs for export production.

Check eligibility

Hydraulic Trailer Classes HT-1 to HT-13

The circular groups modular hydraulic trailer combinations into 13 classes. Gross vehicle weight below excludes the puller tractor, which is taken as a three-axle unit of 25 tonnes with ballast.

ClassAxle rowsGross vehicle weightHow permission is given
HT-1, HT-2, HT-34, 6, 872 t, 108 t, 144 tPermission and fee generated in real time once the route is accepted
HT-4 to HT-910 to 20180 t to 360 tRegional officers review bridges on the route within 7 days
HT-10, HT-118+8, 10+10, turn table bolster288 t, 360 tReview within 7 days, attachment weight declared
HT-12, HT-1314+14, 16+16, girder504 t, 576 tReview within 7 days. Not allowed on bridges other than simply supported types built for special vehicle loading

If the regional officers do not review within 7 days, the portal treats the chosen route as feasible and asks for the fee. Unpaid fees lapse after 7 days and the application starts again.

ODC Permission Process, Stage by Stage

This is the sequence on the MoRTH portal for a National Highway move. Stages 1 and 4 cause most rejections.

1

Stage 1: Drawings and Route Survey

Confirm length, width, height, weight and centre of gravity from the manufacturer’s drawings. Survey bridges, curves, overhead lines and underpasses on the intended route.

2

Stage 2: Portal Registration

Consignor, consignee and transporter each register once. The registered email becomes the login.

3

Stage 3: Cargo Upload

The consignor or consignee uploads the dimensions, origin and destination, signs the declaration and nominates the transporter.

4

Stage 4: Trailer, Driver and Route

The transporter adds the trailer, puller tractor and driver, which the portal checks on VAHAN and SARATHI. The route needs a station every 100 km and an AIS 140 tracking device.

5

Stage 5: Review, Fee and Permit

The fee is charged per 50 km of National Highway by trailer class. Once paid, the portal issues the single-trip permission letter.

6

Stage 6: Movement and Closure

Start within 7 days or extend on the portal. After delivery, the transporter declares trip closure within 15 days.

Planning to move a unit wider than 2.6 m or heavier than a normal trailer can carry? Send us the drawing on WhatsApp for a permit and route check.

Conditions on the Road

Annexure VI of the circular sets the conditions every permitted ODC move must follow.

  • Pilot and markings. A pilot vehicle, danger flags, yellow and black zebra stripes, reflective stickers and red lamps at the extreme edges.
  • Bridge crossings. 5 km/h or less, no braking on the bridge and no other vehicle on it. The transporter’s staff inspect the bridge before and after.
  • Centre line. Keep the load within 300 mm of the carriageway centre line on a bridge.
  • Coupling. Trailers may be coupled end to end, never side by side.
  • Weather. No movement during earthquakes or high wind, with extra care in the monsoon.

The portal covers National Highways only. State highways and city roads fall under the state or local authority, and the transporter arranges those permissions separately.

Choosing the Vessel: Breakbulk, RoRo or Flat Rack

At the port, the choice depends on weight, whether the unit can roll and the lifting gear at both ends.

OptionHow it worksUse it whenWatch for
Flat rack containerCargo lashed to a container base with end wallsOut of gauge units within the line’s weight limit on container routesOut of gauge surcharges and limited slots
BreakbulkLoaded piece by piece into the hold or on deckUnits too large or heavy for flat racksPort handling time and weather exposure
RoRoRolled on and off the ship on wheels or trailersVehicles, wheeled machinery and units on roll trailersHeight and deck load limits
Heavy lift vesselThe ship’s own cranes lift very heavy unitsPorts without shore cranes of the needed capacityLimited sailings and longer planning

Stowage and lashing at sea follow the IMO CSS Code. The lashing plan is checked against the ship’s cargo securing manual by the attending surveyor.

Documents for a Project Move

Road, port and customs read these against each other. The third column is where the move stops.

DocumentWhat is checkedThe mismatch that causes a hold
General arrangement drawingDimensions, weight and centre of gravityDrawing shows the unit without packing or saddles
ODC permission letterRoute, trailer class and declared dimensionsMeasured load larger than declared
Vehicle and driver recordsFitness, permit, insurance and licence on VAHAN and SARATHIA document expires during the trip
Lashing planSecuring points and forcesPlan not approved by the surveyor
Shipping bill and packing listDescription, weight and package marksWeight differs from the permit or the bill of lading

Where Project Cargo Goes Wrong

Most failures come from a figure that changed between the drawing, the permit and the ship.

FailureWhat you seeWhat actually broke
Wrong trailer class on the permitMovement stopped and the permit refused or voidedThe load needed more axle rows than the HT class applied for
Bridge not surveyedRoute objected to by the regional officerA distressed or unsuitable bridge was on the chosen route
Dimensions larger than declared7-day hold, fine and a transporter banThe drawing ignored packing, saddles or the trailer deck
Lashing plan not approvedCargo not loaded on the planned vesselThe plan was not prepared to the ship’s securing manual
Project contract not registeredImported plant assessed item by itemThe contract was not registered before import under the 1986 Regulations

Illustrative Example: The Transformer That Grew

This is an illustrative composite, not a named client. A transformer maker applies for an HT-4 permit using the bare unit’s drawing. On loading, the transport saddles add height and weight beyond what was declared. The move needs a fresh application, and the vessel slot is lost. Measuring the loaded unit on its saddles before applying would have saved the booking.

The Import Side: Project Imports

For plant coming into India, the Project Imports Regulations 1986 let all goods for an eligible project be assessed under one tariff heading, 98.01. CBIC’s taxpayer guide lists industrial plants, irrigation, power, mining and oil or mineral exploration projects.

  • Register first. The contract, with an itemised list attested by the sponsoring authority, must be registered before import.
  • Spares have a cap. Spares, raw materials and consumables are covered up to 10% of the value of the main goods.
  • Some units are excluded. Hotels, hospitals, studios, laundries, garages and workshops do not qualify, nor does a single or composite machine.

What Project Cargo Handling Will Not Do

  1. A permit does not make a bridge safe. Distressed bridges coded red or orange on the portal are closed to all HT classes, and detours add days.
  2. A national permit does not cover state roads. The factory to highway and highway to port stretches may need separate local permissions.
  3. Carrier liability will not cover a transformer. Sea carrier liability is capped per package, so high value units need their own marine policy.

Frequently Asked Questions

What is ODC cargo?

ODC means over dimensional consignment: a single indivisible load whose width, height or length on the vehicle exceeds the limits in Rule 93 of the Central Motor Vehicles Rules 1989. Overweight loads are called OWC.

How to get ODC permission in India?

For National Highways, apply on the MoRTH ODC portal. The consignor uploads the cargo details and nominates a transporter, who adds the trailer, driver and route. Permission is issued online after the fee is paid.

How long does ODC permission take?

HT-1 to HT-3 permissions are generated in real time once the route is accepted. For HT-4 to HT-13, regional officers have up to 7 days to review the bridges on the route.

What is HT-1 to HT-13?

They are the modular hydraulic trailer classes in the MoRTH circular, from HT-1 with 4 axle rows and 72 tonnes to HT-13 with 16+16 axle rows and 576 tonnes. No axle row may carry more than 18 tonnes.

What happens if the cargo is heavier than declared?

The vehicle is held for 7 days and a fine of twenty times the fee is imposed. It may then move only by detouring all bridges, and the transporter is barred from the portal for at least a year.

Do state roads need a separate ODC permit?

Yes. The MoRTH portal covers National Highways only. Stretches on state highways or city roads need permission from the state or local authority that controls them.

What is breakbulk shipping?

Breakbulk means loading cargo piece by piece into a ship’s hold or onto its deck instead of in a container. It suits units too large or heavy for a flat rack.

What is the difference between flat rack and breakbulk?

A flat rack is a container base with end walls that travels on container ships and uses container terminals. Breakbulk is loaded directly into the ship without a container and suits heavier units.

Can imported plant be cleared under one tariff heading?

Yes, under the Project Imports Regulations 1986 and heading 98.01, if the project is eligible and the contract was registered before import. A single machine does not qualify.

Does Rasp International move ODC cargo itself?

No. Heavy haulage, cranes and vessels are provided by specialist partners in our pan-India network. We brief them and check the permit, route and documents. We stay accountable to you.

How Rasp International Handles Project Cargo

Rasp International is an ISO 9001:2015 certified EXIM and DGFT advisory firm in Agra with more than 500 exporters served. For each project move we check the drawings against the permit, match the trailer class to the load and keep the vessel booking and customs filing in step.

See the full partner network on our customs house agent services page.

Get Your Project Move Checked Before You Apply

Send the drawing, weight and origin. We will flag permit class, route and vessel issues before booking.

Sources

This page is general guidance. Circulars, portal screens and bridge restrictions change. Verify against the current MoRTH circular and the ODC portal before you apply or move.

Related: container transportation and flat racks, freight forwarding and Incoterms, EPCG for capital goods and the logistics hub.

Wait - Don't Leave Empty Handed

Get our free 23-Step Export Checklist covering everything from IEC registration to your first shipment. Used by 500+ Indian exporters.

Get the Checklist Free →
No spam. Trusted by exporters across India.
Need help with project cargo handling services? Talk to our team. WhatsApp Call
Chat with us on WhatsApp